Renco Electronics, Inc.
|
||||||
|
||||||
| PURPOSE | ||||||
|
To verify the effectiveness of our quality system and implement any improvements identified. |
||||||
| FORMS/RECORDS | ||||||
|
||||||
| RESPONSIBILITIES | ||||||
| The
QA Manager is responsible for arranging the audit schedule and planning
the majority of the audits. A list of trained auditors will also be used
at each location to conduct all other audits according to the Quality
System Schedule. Audits must be performed a minimum of one (1) time per
year and may not exceed a twelve (12) month period between internal
audits. Auditor training must be scheduled and completed every two (2)
years. If the Internal Audit Checklist (FRM-QA-04) requires any updates, the QA manager must compare the Audit Checklist to the Internal Audit Reports (FRM-QA-02). This is to ensure that the updated Audit Checklist, meets all clauses of the ISO 9001 standard. |
||||||
| PROCEDURE | ||||||
|
|
||||||
|
Updated 10-28-2009 © 2009 Renco Electronics, Inc. |
||||||